Virtual University VU Solved Assignments/Quizzes/GDBs, Past Solved Papers/Assignments/Online Quizzes Solutions.

Sunday, January 31, 2010

Software Project Management Assignment Solution - VUsolutions

Solution #1



Size = 35200 LOC =35.2KLOC (thousand lines of cod)

1: Effort per month

Formula:

E=3.2*(size in KLOC)^1.05

E= 3.2*(35.2)^1.05

=3.2*(42.1)

=135

2: Time per month

Formula:

T= 2.5*(effort)^.38

=2.5*(135)^.38

=2.5*6.45

=16.1

3: No of people required

Formula:

Total no of people needed= effort/ total time to develop

=135/16.1

=8.39




Solution #2



Size = 12000 LOC therefore 12KLOC

1: effort per month

Formula:

E=EAF*3.2*(KLOC)^1.05

E=1.0*3.2*(12)^1.05

=1.0*3.2*(13.6)

=1.0*43.5

=43.5

2: time to develop it

Formula:

2.5*(effort)^.38

2.5*(43.5)^.38

=2.5*4.19

=10.5

3: no of people required

Formula:

Total no of people needed= effort/ total time to develop

=43.5/10.5

=4.14







by VUsolutions VU solutions


No comments:

Post a Comment